PSEG Long Island in Beginning Stages of Proposal To Add Transmission Line From Southampton Village to Deerfield Substation - 27 East

PSEG Long Island in Beginning Stages of Proposal To Add Transmission Line From Southampton Village to Deerfield Substation

icon 1 Photo
PSEG may bury wires in Southampton Village. FILE PHOTO

PSEG may bury wires in Southampton Village. FILE PHOTO

authorCailin Riley on Nov 29, 2023

PSEG Long Island is in the beginning stages of a proposal to install a new underground transmission line that would run from its substation in Southampton Village at the intersection of North Sea Road and West Prospect Street to its Deerfield Substation in Water Mill on Water Mill-Towd Road.

The project would “increase the load capacity and reliability of the electric transmission system” on the South Fork, according to PSEG-LI officials.

The main feature of the project would be the installation of a new underground 138-kilovolt transmission line, which would run primarily along roadways on existing municipal rights-of-way.

An informational session on the project is set for Wednesday, December 6, from 1 to 3 and 5 to 7 p.m. in the Morris Room at Rogers Memorial Library in Southampton Village.

The “Southampton to Deerfield” project, as it’s being called, is being billed by PSEG-LI as “the most cost effective solution to meet the South Fork’s increasing electrical demand and need for reliable electrical service while minimizing disruptions to the community.”

The project is also consistent with the goals of New York’s Climate Leadership and Community Protection Act by supporting the transmission of wind energy on Long Island.

Jeremy Walsh, who works in communications for PSEG-LI, spoke more about why the project is important for area residents.

“This project is necessary because the South Fork continues to see growth in overall electrical demand,” he said. “To prepare for future power needs, PSEG Long Island must ensure it can transfer enough transmission-level voltage electricity between substations, where power is stepped down to lower voltages and sent out into neighborhoods via distribution circuits.”

The current transmission circuit between the substations operates at 69 kilovolts. The new line would augment the existing circuit, providing greater transmission capacity between the substations and creating redundancy, which Walsh said is important in the event that one line is taken out of service for maintenance or repair.

“Because the new transmission line will be underground, it will be protected from storms and severe weather, reducing outages in those situations,” he added.

Overhead and underground transmission lines already exist in the area. This proposed project will involve installing new equipment within the property of the substations, as well as installing an underground line. The plan does not call for any overhead equipment to be added, Walsh said, or for any existing overhead equipment to be removed.

Walsh elaborated further on what the next steps in the proposal would entail.

He pointed out that the voltage level associated with the project requires PSEG-LI to file an application for a certificate of environmental compatibility and public need with the New York State Public Service Commission. The PSC will review the application in detail, as well as hold informational forums and public statement hearings to consider input from the participating parties and the general public. An administrative law judge will preside over the gathering of public comments and all evidence relating to the project, Walsh said. Under New York State law, the PSC may adopt or reject PSEG-LI’s proposal, in whole or in part, or modify it based on the contents of the application and information gathered at public events. Walsh said that process would begin around February 2024 and is expected to take 12 to 15 months to complete.

If the PSC approves the application, an environmental management and construction plan (EM&CP) will be filed in cooperation with the application. The EM&CP details all environmental aspects, engineering design, and construction activities planned for the new underground transmission line.

Once the EM&CP is filed and approved, construction is expected to take between six and nine months. To allow time for all necessary review and approvals, construction would begin in the first or second quarter of 2026.

“The South Fork’s increasing electrical demand and need for reliable electrical service requires an additional investment in the infrastructure,” Walsh said. “This proposed project is a ‘best value’ solution that addresses these needs while minimizing disruptions to the community. In addition to cost, various other factors were considered, including community impact, environmental impact and long-term planning perspectives. This project was selected among the possible solutions because it best addressed these multiple criteria.”

You May Also Like:

Decades After Discrimination, Southampton High School Alumni Reclaim Their Prom Night

Under the lights of 230 Elm, about 70 revelers donned their finest tuxes and dazzling ... 18 Jul 2025 by Michelle Trauring

75 Years of Service: Westhampton War Memorial Ambulance Celebrates Milestone

The Westhampton War Memorial Ambulance Association marked its diamond anniversary with a celebration event on ... 17 Jul 2025 by Dan Stark

Southampton Artists Association Celebrates 25 Years of Art in the Park

In 2000, artistic couple Nancy and Chuck Polis approached the Southampton Village Trustees and mayor ... 16 Jul 2025 by Hope Hamilton

Student-Written Book Published by OLA Offers Real Advice for Navigating Middle School

“Get a good first impression.” “Stay out of drama.” “Beware of the stairs.” These are ... by Dan Stark

Agawam Park WWI Memorial Restoration Gains Momentum With $100K Fundraiser

Growing up in Southampton Village, Robert Giuffra spent a lot of his time at Agawam ... by Cailin Riley

Beachcomber, July 17

I thought I might ease into the social season, but having arrived so late, I ... 14 Jul 2025 by Alex Littlefield

Hampton Coffee and Westhampton Beach High School Marketing Students Design New, Exclusive Coffee Cups

Three students from Westhampton Beach High School have made coffee cup designs that will be ... by Dan Stark

Where Are They Now: Journalist Hope Reese Digs Into a Poisonous Sisterhood in New Book

In the old, abandoned Jewish ghetto of Budapest, there lies the remains of what was ... 13 Jul 2025 by Michelle Trauring

A Trailblazer: Professor Karl Grossman Retires, but the Work Continues

Inside The Cleveland Press newsroom of the 1960s, one word sent Karl Grossman running: “Copy!” ... 11 Jul 2025 by Michelle Trauring

Federal Funding for Public Media Is Close to Becoming a Thing of the Past | 27Speaks Podcast

President Donald Trump issued an executive order on May 1 instructing the Corporation for Public ... 10 Jul 2025 by 27Speaks