Contractors rebuilding the beaches in Sagapoanck and Bridgehampton have asked the Army Corps of Engineers and the U.S. Fish & Wildlife Service for an extension to allow them to work beyond the March 31 deadline after weather delays in February put the project far behind schedule. Only about half of the 6-miles of beach that are to be broadened with more than 1 million tons of sand have been completed. FIRST COASTAL
The beach nourishment project in Sagaponack and Bridgehampton is continuing but is only about half way finished and faces a federal deadline of March 31 to complete the work, because of protections for endangered piping plovers. Southampton Town and the contractors have asked the Army Corps of Engineers for an extension beyond the deadline to allow the work to be completed. DOUG KUNTZ
The beach nourishment project in Sagaponack and Bridgehampton is continuing but is only about half way finished and faces a federal deadline of March 31 to complete the work, because of protections for endangered piping plovers. Southampton Town and the contractors have asked the Army Corps of Engineers for an extension beyond the deadline to allow the work to be completed. DOUG KUNTZ
The beach nourishment project in Sagaponack and Bridgehampton is continuing but is only about half way finished and faces a federal deadline of March 31 to complete the work, because of protections for endangered piping plovers. Southampton Town and the contractors have asked the Army Corps of Engineers for an extension beyond the deadline to allow the work to be completed. DOUG KUNTZ
The beach nourishment project in Sagaponack and Bridgehampton is continuing but is only about half way finished and faces a federal deadline of March 31 to complete the work, because of protections for endangered piping plovers. Southampton Town and the contractors have asked the Army Corps of Engineers for an extension beyond the deadline to allow the work to be completed. DOUG KUNTZ
The beach nourishment project in Sagaponack and Bridgehampton is continuing but is only about half way finished and faces a federal deadline of March 31 to complete the work, because of protections for endangered piping plovers. Southampton Town and the contractors have asked the Army Corps of Engineers for an extension beyond the deadline to allow the work to be completed. DOUG KUNTZ
Contractors rebuilding the beaches in Sagapoanck and Bridgehampton have asked the Army Corps of Engineers and the U.S. Fish & Wildlife Service for an extension to allow them to work beyond the March 31 deadline after weather delays in February put the project far behind schedule. Only about half of the 6-miles of beach that are to be broadened with more than 1 million tons of sand have been completed. FIRST COASTAL
The beach nourishment project in Sagaponack and Bridgehampton is continuing but is only about half way finished and faces a federal deadline of March 31 to complete the work, because of protections for endangered piping plovers. Southampton Town and the contractors have asked the Army Corps of Engineers for an extension beyond the deadline to allow the work to be completed. DOUG KUNTZ
The beach nourishment project in Sagaponack and Bridgehampton is continuing but is only about half way finished and faces a federal deadline of March 31 to complete the work, because of protections for endangered piping plovers. Southampton Town and the contractors have asked the Army Corps of Engineers for an extension beyond the deadline to allow the work to be completed. DOUG KUNTZ
The beach nourishment project in Sagaponack and Bridgehampton is continuing but is only about half way finished and faces a federal deadline of March 31 to complete the work, because of protections for endangered piping plovers. Southampton Town and the contractors have asked the Army Corps of Engineers for an extension beyond the deadline to allow the work to be completed. DOUG KUNTZ
The beach nourishment project in Sagaponack and Bridgehampton is continuing but is only about half way finished and faces a federal deadline of March 31 to complete the work, because of protections for endangered piping plovers. Southampton Town and the contractors have asked the Army Corps of Engineers for an extension beyond the deadline to allow the work to be completed. DOUG KUNTZ
The beach nourishment project in Sagaponack and Bridgehampton is continuing but is only about half way finished and faces a federal deadline of March 31 to complete the work, because of protections for endangered piping plovers. Southampton Town and the contractors have asked the Army Corps of Engineers for an extension beyond the deadline to allow the work to be completed. DOUG KUNTZ
We're happy you are enjoying our content. You've read 4 of your 7 free articles this month. Please log in or create an account to continue reading.
Login / Create AccountWe're happy you are enjoying our content. Please subscribe to continue reading.
Subscribe Already a Subscriber